Case Study: Predictive maintenance cuts downtime by 40%
Sensor data and AI failure forecasting reduced downtime 40% and maintenance cost 20% at an electronics plant.
Context
An electronics plant runs three SMT lines where the pick-and-place machine is the bottleneck. Each unplanned stop costs four to six hours and directly threatens delivery commitments.
Approach
- Fit vibration and temperature sensors on six critical assets and collect three months of data.
- Combine sensor data with maintenance history and operating faults.
- Build per-asset degradation models with a 48–72 hour warning window.
- Wire alerts into the existing maintenance schedule and incident process.
Results after six months
| Metric | Before | After | | --- | --- | --- | | Unplanned downtime hours | Baseline | Down 40% | | Maintenance cost | Baseline | Down 20% | | Spare-part inventory | Baseline | Down 15% | | Alert precision | — | 82% |
Lessons
- Start with the asset where downtime hurts most, not the one that is easiest to instrument.
- An alert is only worth sending if a named person owns it with a response window.
- Operating and maintenance data must live in one place so the model can learn from history.